Metadata-Version: 2.1
Name: python-software-project-estimator
Version: 0.1.2
Summary: Estimate the time and cost of a software project
Author-email: Matthew Sewell <matthew@ragingbits.com>
Project-URL: Hompage, https://artificiallyunintelligent.com
Project-URL: Source, https://github.com/matthewsewell/software-project-estimator
Classifier: Development Status :: 3 - Alpha
Classifier: Intended Audience :: Developers
Classifier: License :: OSI Approved :: MIT License
Classifier: Programming Language :: Python :: 3
Classifier: Programming Language :: Python :: 3.9
Classifier: Programming Language :: Python :: 3.10
Requires-Python: >=3.9
Description-Content-Type: text/markdown
License-File: LICENSE
Requires-Dist: numpy
Requires-Dist: holidays
Requires-Dist: pydantic

# Software Project Estimator

![pylint workflow](https://github.com/matthewsewell/software-project-estimator/actions/workflows/pylint.yml/badge.svg)
![unittest workflow](https://github.com/matthewsewell/software-project-estimator/actions/workflows/unittest.yml/badge.svg)

## Installing

Install using pip:

```
pip install python-software-project-estimator
```

 ## Usage
 Here's an extremely trivial example.
 ```
from datetime import date

from software_project_estimator import Project, Task
from software_project_estimator.simulation.monte_carlo import MonteCarlo


task = Task(name="This is the only task", optimistic=10, pessimistic=22, likely=15)
project = Project(name="My Project", start_date=date(2023, 1, 1), weeks_off_per_year=0)
project.tasks = [task]

monte = MonteCarlo(project, 100_000)
results = monte.run()

for day, result in results.items():
    print(f"{day}: {result}")
 ```

 This will print something like this.
 ```
2023-01-17: total=8 probability=8e-05
2023-01-18: total=80 probability=0.00088
2023-01-19: total=352 probability=0.0044
2023-01-20: total=1104 probability=0.01544
2023-01-23: total=3392 probability=0.04936
2023-01-24: total=7744 probability=0.1268
2023-01-25: total=12528 probability=0.25208
2023-01-26: total=18184 probability=0.43392
2023-01-27: total=19776 probability=0.63168
2023-01-30: total=16656 probability=0.79824
2023-01-31: total=11280 probability=0.91104
2023-02-01: total=5672 probability=0.96776
2023-02-02: total=2312 probability=0.99088
2023-02-03: total=712 probability=0.998
2023-02-06: total=184 probability=0.99984
2023-02-07: total=16 probability=1.0
 ```
 As you can see, the 50% probability mark is somewhere between the 26th or the
 27th of January. This is because the end date is actually the first date on
 which the project is actually finished -- not the last date on which work was
 performed. Let's take a closer look.
 `task.average` tells us that our weighted average outcome should be `15.33`
 person days. Since we only have one person working on this task and we're
 working 5 day weeks, you could look at this and say, "This will take a little
 over three weeks."

 Looking at the calendar, out project started on 1/1/2023, which was a Sunday.
 Also, New Year's day was observed in the US on 1/2. The first day we can
 actually work is 1/3. MLK Day was observed on 1/16, so that's also a day we
 don't work in the US. The 15.33 days we're actually working are 1/3, 1/4, 1/5,
 1/6, 1/9, 1/10, 1/11, 1/12, 1/13, 1/17, 1/18, 1/19, 1/20, 1/23, 1/24, and 1/25.
 That means that, at around the 50% probability, the first day we don't work on
 this project is 1/26.

 This is all well and good but, really, do you want to commit to finishing
 at the 50% mark? You may as well flip a coin to see if you can finish on time.
 What's important here is the *shape* of the outcomes. There's close to a 2/3
 probability that this project can be completed before 1/27 based on our
 three--point estimate. This is probably a decent estimate of how long it will
 take in the real world. What you choose to communicate to the boss is up to
 you.